Business EnvironmentPlan and manage project compliance
A hospice network is replacing its legacy clinical documentation platform. Once migration of active-patient data is verified, a team lead proposes wiping the old system immediately to stop paying its hosting costs. The legacy platform holds more than a decade of patient records that are not part of the migration. What is the most effective approach for the project manager?