Industry pack 02 · Level 1

Foundations

Business EnvironmentPlan and manage project compliance

During preconstruction on a hotel project, a mechanical trade contractor's project manager learns that the boiler plant cannot be placed into service until the state boiler inspector examines the pressure vessels and issues an operating certificate — an inspection only the state authority can perform and that the contractor cannot self-certify. How should the project manager handle this requirement?

Keys: A–D or 1–4 to choose · ⌘/Ctrl+Enter to submit & advance